(Note: Requirements Management is not
considered by TenStep to be a part of the project management
process. Issues management is not an emphasis of the PMBOK.)
|
Project Management Body of
Knowledge (PMBOK) |
TenStep Project Management
Process |
|
4. Project Integration
Management |
|
|
4.1 Project Plan
Development |
1.0 Define The Work 2.0
Build the Workplan |
|
4.2 Project Plan
Execution |
This covers some aspects of TenStep 3.0
through 10.0 as far as the overall management of the project. The
activities in PMBOK 4.2 associated with the actual project work are not
considered a part of the TenStep Project Management Process. They are
considered part of the project work itself. |
|
4.3 Overall Change
Control |
5.0 Manage Scope Change 8.0
Manage Documents 10.0 Manage Metrics |
|
5. Project Scope
Management |
|
|
5.1 Initiation |
The PMBOK project approval
process occurs before TenStep 1.0 Define the Work begins. The rest
of the Initiation Process maps to 1.0 Define the Work. |
|
5.2 Scope Planning
|
1.0 Define the Work,
specifically defining scope in the Project Definition. |
|
5.3 Scope
Definition |
2.0 Build the
Workplan |
|
5.4 Scope
Verification |
1.0 Define the Work,
specifically gaining approval of the Project Definition |
|
5.5 Scope Change
Control |
5.0 Manage
Scope |
|
6. Project Time
Management |
|
|
6.1 Activity
Definition |
2.0 Build the
Workplan |
|
6.2 Activity
Sequencing |
2.0 Build the
Workplan |
|
6.3 Activity Duration
Estimating |
2.0 Build the
Workplan |
|
6.4 Schedule
Development |
2.0 Build the
Workplan |
|
6.5 Schedule
Control |
3.0 Manage the
Workplan |
|
7. Project Cost
Management |
|
|
7.1 Resource
Planning |
2.0 Build the
Workplan |
|
7.2 Cost
Estimating |
2.0 Build the
Workplan |
|
7.3 Cost
Budgeting |
2.0 Build the
Workplan |
|
7.4 Cost Control |
3.0 Manage the
Workplan |
|
8. Project Quality
Management |
|
|
8.1 Quality
Planning |
1.0 Define the Work 9.0
Manage Quality |
|
8.2 Quality
Assurance |
9.0 Manage
Quality |
|
8.3 Quality
Control |
9.0 Manage
Quality |
|
9. Human Resources
Management |
|
|
9.1 Organizational
Planning |
1.0
Define the Work – project level structure, within the context of
organizational structure |
|
9.2 Staff
Acquisition |
2.0 Build the Workplan – in
regards to assigning project resources |
|
9.3 Team
Development |
These soft-skills are not a
part of the TenStep process, but are commented on widely in the Download
Library for Licensed Users |
|
10. Communications
Planning |
|
|
10.1 Communications
Planning |
6.0 Manage
Communication |
|
10.2 Information
Distribution |
6.0 Manage
Communication |
|
10.3 Performance
Reporting |
6.0 Manage
Communication 3.0 Manage the Workplan |
|
10.4 Administrative
Closure |
Not a part of the base TenStep
Process, but included in the 20.0 Related Topics |
|
11. Project Risk
Management |
|
|
11.1 Risk
Identification |
1.0 Define the Work 7.0
Manage Risks |
|
11.2 Risk
Quantification |
1.0 Define the Work 7.0
Manage Risks |
|
11.3 Risk Response
Development |
1.0 Define the Work 7.0
Manage Risks |
|
11.4 Risk Response
Control |
7.0 Manage
Risks |
|
12. Project Procurement
Management |
|
|
12.1 Procurement
Planning 12.2 Solicitation Planning 12.3 Solicitation 12.4 Source
Selection 12.5 Contract Administration 12.6 Contract
Closeout |
Procurement is not emphasized
in TenStep because of the belief that this tends to be driven by a
separate Procurement / Contracts Department. The Project Manager may
execute parts of the process, but they do not own the process. There is
some information in 20.0 Related Topics. |
| Other |
Other |
|
Issues management is not an
emphasis of the PMBOK. |
4.0 Manage
Issues |
|
Document management is
mentioned as a part of 4.3 Overall Change Control, but is not
emphasized. |
8.0 Manage
Documents |